Apply     Visit     Give     |     Alumni     Parents     Offices     TCNJ Today     

Current Projects

Construction Website Update as of March 27, 2018

 If there are any questions or concerns regarding any of these projects,

please contact Campus Construction at 609-771-3234, or email jamest@tcnj.edu.

 

Security Cameras Phase V @ Dorm entrances: has started in the field and will continue through the spring and early summer.

Brower Student Center Renovation and Addition: in close out. New STEM Building and Chemistry addition: in close out.

New STEM Building and Chemistry addition: in close out.

STEM Phase II/Chemistry renovations: work in the field is progressing and will continue in various areas of the complex though the summer and into the fall semester.

Stadium storage building: substantially completed and in close out.

Loser lower level Nursing Suite renovation: bids have been received, work will begin in the field right after commencement in May.

Campus fire water piping: work along Metzger on the south side has been installed and will be cleaned up in the spring. Currently working at Travers and Wolfe. Piping in the Admin parking lot will begin around April 15th.Work in the Green Lawn will take place after Commencement.

Flower Hill Dam removal: in close out

Travers and Wolfe Elevator Replacements: contractor is on board. Work in the field will begin right after students leave for the summer break.

Kendall Hall Lab upgrade: complete, in close out.

Culvert Emergency work: majority of concrete and underground is work is completed. Will clean up and pave in April.

Forcina HVAC Replacement and Roof Replacement: design is being finalized and will be bid in early 2018 for work to take place to replace

all HVAC in the building and replace the roof.

Maint. Bldg. Window Replacements: will be bid in spring. Work in the field will take place over the summer and into the fall.

Packer Hall Pool Deck Replacement: contractor is board, work in the field will start right after Special Olympics in June.

‘68 Wing of Old Library Roof Replacement: design documents are being finalized now for bidding in 2018 to be done over the summer/fall of 2018.

Social Sciences Atrium Rejuvenation: most work in the field is completed. New furniture will be installed over the summer.

Roscoe Hall Garden: work in the field has begun. Should be completed in mid-April.

Brower Student Center Landscaping Project: the contractor has mobilized and work will continue through July.

Armstrong Hall Renovation: Will be bid in the spring/summer. Work will take place in the field all of 2019.